Some facts and figures about the Ifinger ferrata

  • 28 January 2016: geological survey by Alpine geology
  • 5 February 2016: definitive project (Tourism Association Schenna)
  • 14 April 2016: Preparatory work and start of construction (Company  Erdbau, mountain guide)
  • 15 July 2016: Activation of the counting device (eco counter)
  • 21 July 2016: First ascent
  • 12 August 2016: End of construction
  • 24 September 2016: Official inauguration and opening (Piffinger Köpfl, Merano 2000)
  • 29 October 2016: best-visited day with 488 entries 
  • 11 December 2016: 10,000th mountaineer
  • 15 December 2016: Registration of the mark “via ferrata Heini Holzer” (National/ international)
  • 1,000 meters steel cable
  • Performance of 5 mountain guides; 1,215 hours
  • 10,560 entries from 15 July until 31 December 2016
  • 87 entries/day (average during the season from 15 July to 5 November 2016)
  • 145 entries on Saturday and Sunday (average during the season from 15 July to 5 November 2016)