Some facts and figures about the Ifinger ferrata
- 28 January 2016: geological survey by Alpine geology
- 5 February 2016: definitive project (Tourism Association Schenna)
- 14 April 2016: Preparatory work and start of construction (Company Erdbau, mountain guide)
- 15 July 2016: Activation of the counting device (eco counter)
- 21 July 2016: First ascent
- 12 August 2016: End of construction
- 24 September 2016: Official inauguration and opening (Piffinger Köpfl, Merano 2000)
- 29 October 2016: best-visited day with 488 entries
- 11 December 2016: 10,000th mountaineer
- 15 December 2016: Registration of the mark “via ferrata Heini Holzer” (National/ international)
- 1,000 meters steel cable
- Performance of 5 mountain guides; 1,215 hours
- 10,560 entries from 15 July until 31 December 2016
- 87 entries/day (average during the season from 15 July to 5 November 2016)
- 145 entries on Saturday and Sunday (average during the season from 15 July to 5 November 2016)